The first of two dormitory sections of the LNG Canada camp at Kitimat is now being assembled. (Photo courtesy LNG Canada)                                One of the more visible above-ground projects now underway is that of the worker camp, Cedar Valley Lodge. (Contributed photo)

The first of two dormitory sections of the LNG Canada camp at Kitimat is now being assembled. (Photo courtesy LNG Canada) One of the more visible above-ground projects now underway is that of the worker camp, Cedar Valley Lodge. (Contributed photo)

Workers’ camp at LNG facility in Kitimat takes shape

Extensive worker camp now being assembled

Born in Ireland but having spent years overseeing liquefied natural gas (LNG) construction projects in Australia, LNG Canada’s just-arrived general manager for its $40 billion facility in Kitimat is firm about his expectations.

“We want this to be the safest project on earth,” Vince Kenny says of construction which has just passed the one year mark leading to a planned finish in 2024.

With just under 1,000 people now working at the 400-hectare site, now is the time to cement that standard, he says.

“By the time we get to 5,000 people, we will have that culture in place,” Kenny emphasizes that this project which will be his seventh. “Unless we’ve got a culture, all the systems, processes and procedures are ineffective.”

Employees begin each shift reviewing the work plan, a procedure called a toolbox discussion.

“We’re here to take care of one another,” says Kenny, translating the IIF acronym that’s the hallmark of LNG Canada — Incident and Injury Free.

Even a brief tour of the works by a group of journalists from across B.C. starts with a video of LNG Canada workers outlining safety and security, the two words being almost interchangeable.

Workers have ID cards to be ‘badged in,’ creating an electronic record of their presence. They’re required to stay within their designated work area. There are constant security patrols. Vehicles are inspected for any fluid leaks before entry. There’s specific mention of drug-sniffing dogs too.

READ MORE: Okanagan company wins contract for LNG Canada project in Kitimat

No one gets on the site without basic safety equipment — hardhat, safety glasses, a high visibility vest, work boots and gloves. The driver of the tour bus taking the journalists to the site points out emergency exit windows. He brandishes a small hammer to smash a window if necessary. The bus doesn’t move until each passenger clicks in their seatbelt.

Victor Kenny, LNG Canada general manager

With Kenny is Trevor Feduniak who arrived in Kitimat in mid-2016. As the project site manager, he was one of the first senior LNG Canada people on location, overseeing the clearing of the former Methanex site and then expanding its footprint.

Although the project was not given the formal go-ahead until last October by LNG Canada’s investors Shell, PETRONAS from Malaysia, PetroChina from China, Mitsubishi Corporation from Japan and Korean-owned KOGAS, crews had been fully occupied raising up the location to a construction standard and to safeguard it against the possibility of tsunami sweeping inland from the Douglas Channel.

The fill comes from the nearby Sandhill, a mountain of material Feduniak describes as perfect for its material composition. One million cubic metres has already been transferred, edging away at the overall 2.5 million cubic metres that will have to be moved and placed in preparation for the arrival of two massive processing modules. From there, the gas will be transported via a pipeline from northeastern B.C., super-cooled to a liquid state for storage and then shipped out on specialized tankers to Asian customers.

“This is what we call coming out of the ground,” Feduniak explains as a tour bus winds its way through the site, encountering massive material-carrying trucks along the way.

Two streams that cross the site, the Kitimat Side Channel and Beaver Creek, were diverted to ensure Fluor-JGC has dry and stable conditions on which to construct the plant.

“When you disturb one habitat, you have to compensate with two [enhancement measures],” says Feduniak of the environmental work that was involved.

He compares the detailed water course replacement work for fish and other habitat to that of a landscaped Japanese garden.

One corner of the project site contains what, to the untrained eye, looks like sections of pipe stacked metres above the ground.

What they are are the pilings, 40 metres long, that will be driven into the ground upon which the two processing buildings will sit.

READ MORE: LNG Canada cost to exceed stated $40 billion price tag

Those processing modules being built in Asia are to be 70 metres long, 35 metres wide and 50 metres tall, the approximate height of a 13-storey commercial building.

They’ll be shipped to Kitimat in modular segments and assembled on-site, being transported to their final resting place via an elaborate series of interconnected trailers with hundreds of wheels controlled by a single operator using a remote control. So sophisticated is the transport system that the operator is able to place the modules within centimetres of where they need to be located.

The sheer height of the modules has meant raising Rio Tinto BC Works’ power lines that cross the site to deliver power to the smelter from Kemano, so that the modules can fit comfortably underneath when being moved.

One of the more visible above-ground projects now underway is that of the worker camp, Cedar Valley Lodge, which is being built by the ATCO-Bird joint venture, for another joint venture between Fluor Corporation and JGC, the overall general contractor on the project.

There’ll be two living unit sections with a series of common buildings in the middle.

One of the modular accommodation sections is now being assembled with a finishing schedule of next spring to meet a first goal of 1,500 “heads in beds” with 1,000 more beds to be added each quarter thereafter to the final total of 4,500.

Unlike camps of past, each worker will have his or her own bathroom and each room will have its own TV. There’ll be sound dampening and other acoustic methods so that sleeping quarters will be as quiet as possible. The living areas will be co-ed.

The middle buildings will contain administration offices, sports and recreation facilities including male and female gyms, kitchen and dining facilities, an entertainment centre, a licensed lounge, a medical clinic, storage for luggage and housekeeping and maintenance facilities.

There’ll be landscaping around the area and informational material describes the facility as having the “largest core footprint” of its kind in Canada.

“You want your workers to come here and then want to come back,” said LNG Canada spokesperson Susannah Pierce of the atmosphere and amenities of the facility.

More than 4,500 people will be onsite at any one time at the peak of construction, requiring between 7,000 to 7,500 people in all given the shift work nature of the project. Workers will be onsite for 14 days at a time, returning after a seven-day break.

All this compares to another large worker camp in B.C. — the 1,600-room facility at B.C. Hydro’s Site C project in northeastern B.C.

With accommodation facilities now underway, there’s other activity on the waterfront at two terminal sites.

LNG Canada is building Rio Tinto a new wharf in exchange for taking over the aluminum smelting company’s existing wharf. Dredging is now going on as part of that project.

kitimatLNGlng canada

Get local stories you won't find anywhere else right to your inbox.
Sign up here

 

LNG Canada project site manager Trevor Feduniak arrived in Kitimat in mid-2016. (Natalia Balcerzak/Terrace Standard)

LNG Canada project site manager Trevor Feduniak arrived in Kitimat in mid-2016. (Natalia Balcerzak/Terrace Standard)

LNG Canada’s ‘fish ladder’ at Anderson Creek, which allows fish to migrate despite construction-related work. (Natalia Balcerzak/Terrace Standard)

LNG Canada’s ‘fish ladder’ at Anderson Creek, which allows fish to migrate despite construction-related work. (Natalia Balcerzak/Terrace Standard)

The middle buildings will contain administration offices, sports and recreation facilities including male and female gyms, kitchen and dining facilities, and other features. (Natalia Balcerzak/Terrace Standard)

The middle buildings will contain administration offices, sports and recreation facilities including male and female gyms, kitchen and dining facilities, and other features. (Natalia Balcerzak/Terrace Standard)

Just Posted

An aerial shot of Cedar Valley Lodge this past August, LNG Canada’s newest accommodation for workers. This is where several employees are isolating after a COVID-19 outbreak was declared last Thursday (Nov. 19). (Photo courtesy of LNG Canada)
Forty-one positive COVID-19 cases associated with the LNG Canada site outbreak

Thirty-four of the 41 cases remain active, according to Northern Health

Cases have gone up in Northern Health in the past week, as they have all over B.C. (K-J Millar/Black Press Media)
Northern Health reports new highest number of COVID-19 cases in one day

Nineteen cases were reported to Public Health last Tuesday (Nov. 17)

FILE – British Columbia provincial health officer Dr. Bonnie Henry wears a face mask as she views the Murals of Gratitude exhibition in Vancouver, on Friday, July 3, 2020. THE CANADIAN PRESS/Darryl Dyck
Masks now mandatory in all public indoor and retail spaces in B.C.

Many retailers and businesses had voiced their frustration with a lack of mask mandate before

(Photo courtesy of LNG Canada)
An aerial shot of Cedar Valley Lodge this past August, LNG Canada’s newest accommodation for workers. This is where several employees are isolating after a COVID-19 outbreak was declared Thursday.
COVID-19 outbreak at LNG Canada Project site

14 employees have tested positive for COVID-19 at this time

The ban is only applicable to ICI cardboard and does not extend to residential cardboard. (Priyanka Ketkar photo/Lakes District News)
RDBN to reinstate ICI cardboard ban at Knockholt Landfill starting Dec. 6

Private bailing facility to take the cardboard starting next year

People wearing face masks to help curb the spread of COVID-19 cross a street in downtown Vancouver, on Sunday, November 22, 2020. The use of masks is mandatory in indoor public and retail spaces in the province. THE CANADIAN PRESS/Darryl Dyck
B.C. reports 17 COVID deaths, 1,933 new cases as hospitalizations surge over the weekend

There are 277 people in hospital, of whom 59 are in ICU or critical care

Workers arrive at the Lynn Valley Care Centre seniors home, in North Vancouver, B.C., on Saturday, March 14, 2020. It was the site of Canada’s first COVID-19 outbreak in a long-term care facility. THE CANADIAN PRESS/Darryl Dyck
Rapid tests ‘not a panacea’ for care homes, Dr. Bonnie Henry says

B.C. lacks capacity for daily tests of thousands of workers

(Delta Police Department photo)
Cannabis edibles found in Halloween bag lead B.C. police to illegal lab

Delta police arrested a man and a woman while executing a warrant at a residential property Nov. 20

A woman being arrested at a Kelowna Value Village after refusing to wear a mask on Nov. 22.(@Jules50278750/Twitter)
VIDEO: Woman arrested for refusing to wear mask at Kelowna Value Village

RCMP claims the woman was uncooperative with officers, striking them a number of times and screaming

Join Black Press Media and Do Some Good
Join Black Press Media and Do Some Good

Pay it Forward program supports local businesses in their community giving

B.C. Liberal MLA Shirley Bond questions NDP government ministers in the B.C. legislature, Feb. 19, 2020. (Hansard TV)
Cabinet veteran Shirley Bond chosen interim leader of B.C. Liberals

28-member opposition prepares for December legislature session

Motorists wait to enter a Fraser Health COVID-19 testing facility, in Surrey, B.C., on Monday, November 9, 2020. THE CANADIAN PRESS/Darryl Dyck
COVID-19: What do rising positivity rates mean for B.C.? It’s not entirely clear

Coronavirus cases are on the rise but the province has not unveiled clear thresholds for further measures

A rider carves a path on Yanks Peak Saturday, Nov. 21. Two men from Prince George went missing on the mountain the next day. One of them, Colin Jalbert, made it back after digging out his sled from four feet under the snow. The other, Mike Harbak, is still missing. Local search and rescue teams went out looking Monday, Nov. 23. (Sam Fait Photo)
‘I could still be the one out there’: Snowmobiler rescued, 1 missing on northern B.C. mountain

As Quesnel search and rescue teams search for the remaining rider, Colin Jalbert is resting at home

More than 70 anglers participated in the bar-fishing demonstration fishery on Sept. 9, 2020 on the Fraser River near Chilliwack. DFO officers ticketed six people and seized four rods. A court date is set for Dec. 1, 2020. (Jennifer Feinberg/ Chilliwack Progress file)
Anglers ticketed in Fraser River demonstration fishery heading to court

Sportfishing groups started a GoFundMe with almost $20K so far for legal defence of six anglers

Most Read